Tuesday, December 11, 2007

Sprint 2 Started

The first sprint was aborted because of sucessive delays(maybe a topic of another post), Sprint 2 was better planned to avoid this kind of problem.
  • Planning: 12/08/2007
  • Sprint Start: 12/09/2007
  • Sprint End: 12/22/2007
  • Planned Backlog Itens:
    1. Prepare Infrastructure.
    2. As an administrator, I want to add a product and it will have e backlog.
    3. As an user, I want a product and its sprint backlog visible on the screen.
  • Planned meetings with the client
    1. 12/05/2007
    2. 12/12/2007
    3. 12/19/2007
Artifact Delivery Date
Test Stories Document (version 1: revised) 12/12/2007
Quality Assurance Plan(draft 1) 12/13/2007
Data Model(draft 1) 12/12/2007
FireScrum alpha 1 12/20/2007

We are keeping our user stories(while FireScrum isn't ready) in Rally community version.

Current Burn Down:


Saturday, December 1, 2007

First lines of code!

Today we started coding and the high-level architecture was created, you can check it in our svn at https://firescrum.svn.sourceforge.net/svnroot/firescrum.